Environmental Situation |
| Site: |
-
Former chrome plating
facility and truck terminal
-
Significant blight
-
Centrally located near
downtown Milwaukee
-
1 mile from the new $400
million Miller Park stadium
|
|
Environmental: |
-
Asbestos throughout the
former facility
-
Lead and chromium impacts
-
Petroleum-saturated soils
near an old tank
|
| |
|
|
Action: |
Working closely with the Village
of West Milwaukee and the
Wisconsin Department of Natural
Resources, RER developed a WNDR
approved Remedial Action Plan.
Remediation and construction
completed 2003. Building
completed in 2003, 100%
occupied.
|
| |
|
|
Outcome: |
-
50,000 square foot
speculative office/warehouse
-
Tax Base increase of over $2
million
-
Over 50 new jobs
|
|
|