Jostens
Princeton, IL

 

 

 


Before


Remediation Underway

Environmental Situation
Site:
  • Operating facility with environmental impacts
Environmental:
  • Significant TCE free product
  • VOC plume moving off site
  • Jostens set up a $6.6 million reserve for the remediation
  • Expected to take 6 – 10 years for closure
 
 
Action: Reporting to Jostens’ General Counsel, RER served as the strategic project manager for the investigation and remediation of the environmental contamination. Working strategically with Jostens’ legal counsel and environmental engineers, RER leveraged its expertise in quick, low-cost remediation to get a response action plan approved by the state of Illinois.  RER’s experience also assisted Jostens’ legal counsel in cost recovery.
 
 
 
Outcome:
  • Remediation cost under $2 million

  • Results in 2 years